Rewriting the rules of PPPs: Inside SL’s new 2026 PPP Bill

Rewriting the rules of PPPs: Inside SL’s new 2026 PPP Bill

23 Nov 2026 | BY Nuwan Peiris


For decades, public-private partnerships (PPPs) in Sri Lanka have operated in an uneasy twilight zone – caught between Executive policy circulars, ad-hoc Cabinet of Ministers memoranda, and fragmented procurement rules. While the promise of private capital and operational efficiency has long appealed to successive Governments, the absence of a dedicated Statutory architecture often left major infrastructure projects vulnerable to opaque unsolicited bids, skewed risk-sharing, and unmonitored contingent liabilities on the national balance sheet.

This month (November), the Government moved decisively to close that Legislative gap. Published in the Gazette Supplement on 10 November, by the order of the Finance, Planning and Economic Development Minister, the PPP Act (PPPA) Bill seeks to fundamentally overhaul how Sri Lanka identifies, assesses, procures, and governs long-term infrastructure and public service partnerships.

At roughly 90 pages of detailed Statutory text, the Bill does far more than establish a new State agency. It anchors PPPs squarely within the broader public financial management reforms, places strict guardrails around unsolicited proposals, and erects Statutory firewalls against post-bid contractual dilution. For taxpayers, investors, and public administrators alike, understanding how this Legislation works is essential.


Anchoring PPPs in public financial discipline


The foundational premise of the Bill is explicit in its Preamble: PPPs belong firmly under the domain of public finance. Rather than treating a PPP as an off-budget shortcut to build roads, ports, energy facilities, or digital infrastructure without immediate Treasury outlay, the Bill integrates every stage of the PPP lifecycle into the Public Financial Management Act (PFMA), No 44 of 2024.

Under Section 2 of the Bill, the PFMA remains supreme – if any inconsistency arises between the two Statutes, the PFMA prevails. At the same time, the new Bill overrides any other conflicting written laws specifically governing PPPs. This dual hierarchy ensures that fiscal risk, sovereign guarantees, and contingent liabilities cannot bypass Treasury scrutiny, while simultaneously replacing the patchwork of older administrative guidelines with a single Statutory code.

To prevent small, routine public works from being bogged down in complex PPP structuring, the Bill applies only to projects whose estimated total cost at initiation equals or exceeds a minimum financial threshold prescribed by the Minister. Once determined at initiation, that valuation is conclusive –  meaning that subsequent cost overruns or reductions will not arbitrarily strip a project of its Statutory governance framework.

Existing contracts signed before the Bill comes into force remain governed by the Legal regime in place when they were executed, preserving contractual sanctity and investor confidence. However, both contracting authorities and private partners on existing projects will still be required to submit operational data for national monitoring and database tracking, subject to existing confidentiality protections.


A facilitator, not a deal-maker: The new national agency


A centrepiece of the Bill is the establishment of the National Agency for PPPs as a corporate body. Yet, unlike some centralised investment authorities of the past that combined policy promotion with direct deal-making, the Bill deliberately separates advisory facilitation from procurement execution.

The Agency’s mandate is to build institutional capacity, issue standardised methodologies, review feasibility studies, assess contingent liabilities, and maintain a centralised national PPP pipeline. Crucially, Section 49 expressly prohibits the Agency from participating in the selection of a private partner, engaging in procurement, or conducting contract negotiations.

Those powers remain with the relevant contracting authority – whether a line Ministry, a Government Department, a Provincial Council, or a State-Owned Enterprise – operating strictly under the procurement guidelines issued by the independent National Procurement Commission (NPC) pursuant to Article 156C(1) of the Constitution.

Governance of the Agency itself reflects an effort to insulate technical appraisal from political interference. Its Board comprises two senior Treasury/Investment officials, a Chartered Accountant specialising in infrastructure financial modeling nominated by the Institute of Chartered Accountants, and four multidisciplinary experts appointed across law, finance, engineering, logistics, economics, and project management. Board members are barred from serving or advising any private PPP partner for two years after vacating office, and the entire Agency is designated as a Scheduled Institution under the Anti-Corruption Act, No 9 of 2023.


Ending ‘PPP first’ assumptions: Mandatory value-for-money gateways


One of the most consequential reforms in Part III of the Bill is Section 36, which imposes an outright ban on predetermining a public project as a PPP before a formal pre-feasibility or feasibility study is completed.

In the past, infrastructure proposals were frequently earmarked for private concessions before anyone rigourously tested whether traditional State procurement might be cheaper or less risky. Under the new framework, a contracting authority must assemble a multidisciplinary project team and pass through three mandatory gateways before the Public Investment Committee can even consider recommending a project to the Cabinet: Identification report (Lodged with the National Planning Department to align the project with the national Public Investment Plan, reviewing land acquisition, resettlement, preliminary environmental impacts, and stakeholder acceptability), Preparatory study (Required for all projects to evaluate the economic feasibility, risk allocation, fiscal affordability, climate resilience, and indicative value for money), and a Full feasibility study (Mandatory for "major projects" exceeding a prescribed cost threshold, establishing economic internal rates of return, net present value, exact heads of terms, and proof that the PPP modality delivers the highest value for money).

The Bill defines "value for money" not merely as the lowest upfront price tag, but as a multi-criteria balance of whole-of-life costs (design, building, finance, and maintenance), monetised risk transfer, service quality, and long-term public interest.


Taming unsolicited proposals


Few areas of Sri Lankan infrastructure development have generated more controversy than unsolicited proposals – projects pitched directly to the State by private promoters outside a competitive tender. While unsolicited ideas can bring genuine innovation, they have historically invited criticism for bypassing open price discovery.

Section 50 subjects unsolicited proposals to a rigourous filtering mechanism. First, an unsolicited proposal cannot even be entertained if the project already appears in an announced selection process or an existing Government project pipeline. Second, the contracting authority must determine that the proposal serves the public interest before requiring the private initiator to fund and submit full technical, commercial, environmental, and social feasibility documentation.

Most importantly, even after an unsolicited proposal clears Agency review, Committee prioritisation, and Cabinet approval, it cannot be awarded directly by private treaty. Section 50(3)(h) mandates that the contract award must undergo a competitive tender procedure under the Commission’s guidelines to test market competition. Furthermore, if a private initiator fails to meet the strict implementation timelines set by the Committee, the Committee holds sole, non-reviewable discretion to terminate the project.


Locking the contract before bidding – and preventing post-award creep


A recurring failure point in the international PPP practice occurs after a preferred bidder is chosen: during protracted post-bid negotiations, risk allocation quietly shifts back onto the public sector, tariffs rise, or sovereign guarantees expand.

Sections 51 and 52 directly outlaw this practice. The full PPP contract – not merely a broad memorandum of understanding – must be finalised and included in the bidding documents when formal proposals are solicited. Once a winning bidder is selected, Section 52(3) imposes an absolute bar on any negotiations or amendments prior to signing, overriding even general procurement guidelines if a discrepancy exists.

Even after a contract is signed and operational, Section 53 restricts post-award modifications. Any "substantial" amendment – defined as altering the private partner’s remuneration by more than five per cent in the present value, expanding the scope of works or services by more than 10%, changing conditions in a way that would have attracted different bidders initially, or replacing the private partner – cannot be agreed quietly between a Ministry and a contractor. Such changes require fresh vetting by the Agency, the Department, the Committee, and the Minister, who may mandate re-tendering the entire contract.


Balancing investor bankability with public safeguards


While the Bill tightens public oversight, Part VII recognises that private lenders and equity investors will not commit long-term capital (defined generally as five to 30 years) without clear legal predictability.

The Legislation expressly authorises the State – subject to the PFMA and the Public Debt Management Act, No 33 of 2024 – to provide structured support where justified by feasibility studies, including availability payments, viability-gap grants, land access, minimum off-take commitments, and tax incentives. It also empowers private partners to grant security interests over project receivables and corporate shares to raise project finance, while strictly prohibiting any encumbrance over underlying public property or core public service assets.

To ensure uninterrupted public services if a private operator defaults, Section 58 codifies clear "step-in rights." Both the contracting authority and senior project lenders (under direct agreements) may temporarily step in to manage operations or substitute a failing contractor, with the State retaining priority over assets of strategic or national security importance.

For ordinary citizens, Section 65 and Section 70 enshrine enforceable consumer protections: non-discriminatory access, equal pricing for users in equivalent circumstances, continuous service standards, and mandatory, accessible public grievance and claims-handling mechanisms maintained by the private operator.


Transparency, SL governing law, and dispute resolution


Finally, the Bill addresses two long-standing public concerns: secrecy and foreign legal entanglement.

Under Section 71, every PPP contract must be governed by the laws of Sri Lanka, and related financing or direct agreements must likewise follow Sri Lankan law unless the Government expressly agrees otherwise. While unresolved disputes proceed to arbitration after structured partnering and dispute-avoidance meetings, the Bill stipulates that the arbitration forum cannot be dictated unilaterally by the private partner’s financiers.

On transparency, Section 78 requires the Agency to maintain a publicly accessible online database containing signed PPP contracts (with only narrowly defined commercially sensitive details redacted within the bounds of the Right to Information [RTI] Act, No 12 of 2016), alongside summaries of fiscal commitments, Government guarantees, termination liabilities, and annual performance reports.


Watchouts and statutory weaknesses


Despite its strong architecture, the Bill leaves critical execution risks unaddressed. Key thresholds – including the "prescribed threshold" for applicability (Section 2[1][a]), the "transitional threshold" for pre-existing Cabinet-approved projects (Section 2[1][e]–[f]), and the cost floor separating "major projects" requiring full feasibility studies from smaller ones requiring only preparatory studies (Section 38[1][b]–[c], [2]) – are deferred to Ministerial regulations, creating uncertainty until gazetted.

Further friction may arise where the Bill defers to external instruments. Inconsistencies yield to the PFMA (Section 2[3]), while procurement turns on Commission guidelines (Sections 49-50) that may not yet exist in full form – triggering fallback unsolicited proposal rules (Section 50[2]).

Meanwhile, Ministerial discretion under Section 2(1)(h)–(k) to pull active pre-enactment procurements into the Act, Cabinet exemption powers (Section 2[1][j]), and broad Government support and sovereign guarantee options (Section 64[1]–[2]) require strict fiscal discipline so that exceptions do not dilute statutory safeguards. Finally, Agency database disclosures remain subject to confidentiality rules and RTI exemptions (Section 78[1]–[2]), testing real-world transparency.


The road ahead


Legislation alone cannot build a port, modernise a power grid, or deliver efficient public transport. Much will depend on the speed and rigour with which the Minister promulgates the accompanying regulations – particularly the financial thresholds separating routine projects from major ones – and how swiftly the Commission issues its tailored PPP procurement guidelines.

Yet, by subjecting PPPs to mandatory value-for-money testing, forcing unsolicited proposals into open competition, banning post-bid contractual renegotiations, and placing sovereign guarantees under public scrutiny, the Bill lays down the clearest institutional rules of engagement that Sri Lanka has ever had. If faithfully enforced, it offers a pathway to attract serious, long-term private investment without mortgaging the public purse.

The writer is an attorney


……………..