Post-Ditwah, recovery remains unfinished

Post-Ditwah, recovery remains unfinished

29 Nov 2026 | By Methmalie Dissanayake and Danara Kulathilaka


One year after Cyclone Ditwah struck Sri Lanka’s eastern coast, the National Building Research Institute (NBRI) says it has cleared land to resettle 34,000 families, although only about 1,700 high-risk families need to be relocated. 

However, the Civil Society Collective for Malaiyaha Reconstruction (CCMR) says that not a single permanent house has been built for displaced plantation families, while about Rs. 11 billion in donations to the Rebuilding Sri Lanka initiative remains unspent.

The cyclone made landfall on 28 November 2025, and a State of Public Emergency was declared the same day. 

A Post-Disaster Needs Assessment (PDNA), conducted in early 2026 by the Disaster Management Centre (DMC) and the National Planning Department under the Rebuilding Sri Lanka Presidential Task Force, put the combined effect of the disaster at Rs. 1,034.1 billion and three-year recovery needs at Rs. 1,022.5 billion. 

The World Bank, the European Union, the United Nations (UN), the Asian Development Bank (ADB), and the Asian Disaster Preparedness Center provided technical assistance.


The storm and its toll


Rainfall ranged from 150 mm to 500 mm across the affected river basins, with Gammaduwa in Matale recording a peak of 545 mm over two days, according to the PDNA. Runoff from the central highlands overflowed the Kelani River, Kala Oya, Malwathu Oya, and Mahaweli River, and an estimated 1.1 million hectares, roughly 20% of the country’s land area, were inundated, exposing more than 2.2 million people across the 22 districts assessed. 

The NBRI documented 1,991 landslide events in December 2025. The PDNA stated that unregulated land-use changes, deforestation, and rapid construction in high-gradient catchments had weakened natural slope retention, and that World Weather Attribution analyses indicated that warming and negative Indian Ocean Dipole conditions had intensified the rainfall, aligning it with a 1-in-30-year return period.

By mid-January 2026, DMC reports confirmed 646 deaths and 173 missing persons. Displacement peaked in early December at 232,752 people in 1,441 safety centres. By 19 January, 169,642 people remained displaced, mostly with host families or in rented accommodation, and a UN report in March put the figure at more than 149,000.

Existing vulnerabilities limited coping capacity, with a poverty rate of 25.9% and an informal labour share above 67%, the PDNA noted. Acute food insecurity doubled in the affected districts, from 16% to 32%, by late December, and UNICEF identified 281,830 children under five, 19,021 pregnant women, and 96,637 breastfeeding mothers as nutritionally at risk. 

Some 149,400 workers lost five million workdays and an estimated Rs. 5.5 billion in wages. Daily wage earners, informal traders, and central highlands tea plantation workers were hit hardest, and female estate workers also faced heavier unpaid care responsibilities.


Counting the cost


The Rs. 1,034.1 billion total comprises Rs. 618.1 billion in physical damage and Rs. 416.0 billion in economic losses. Infrastructure sustained the largest share of damage, at Rs. 382 billion, led by transport at Rs. 295.7 billion. Heavy rainfall damaged 1,206 km of national roads, 1,956 km of provincial roads, 3,650 km of rural roads, 805 km of railway track, and 750 bridges.

A total of 113,777 homes were damaged, of which 5,945 were fully destroyed, and more than 24,900 households require relocation out of designated landslide ‘red zones’. Productive sectors suffered mainly flow losses: commerce and industry recorded Rs. 151.3 billion in losses against Rs. 61.3 billion in damages, affecting 45,166 enterprises, while agriculture recorded losses worth Rs. 136.7 billion against Rs. 25.4 billion in damages after 109,965 hectares of paddy were inundated during the Maha season. 

More than 1,400 irrigation structures were destroyed and the environment sector lost Rs. 65 billion. Recovery needs were concentrated in Kandy (Rs. 154.6 billion), Nuwara Eliya (Rs. 126.1 billion), Badulla (Rs. 97.9 billion), Puttalam (Rs. 78.4 billion), Kegalle (Rs. 63.8 billion), and Colombo (Rs. 44.4 billion).

The PDNA split the requirement into Rs. 391.3 billion for the first 12 months and Rs. 631.2 billion for the following 12–36 months, which covers permanent relocation, slope stabilisation, and road and bridge reconstruction. Reconstruction costs include a 15–25% premium for Build Back Better standards.

Parliament approved a Rs. 50 billion supplementary relief budget for late 2025 and earmarked Rs. 500 billion for 2026 reconstruction. The Ceylon Electricity Board spent Rs. 23.8 billion restoring power to 4.1 million consumers within two weeks, and the National Disaster Relief Services Centre processed more than 40,000 assistance requests. 

Under Budget Circular No.08/2025, households received Rs. 25,000 for cleaning and Rs. 50,000 for emergency repairs, with rental support of up to Rs. 25,000 a month, while housing grants ranged from Rs. 250,000 for partially damaged homes to Rs. 5,000,000 for fully destroyed ones. The UN’s Humanitarian Priorities Plan sought $ 35.3 million, of which $ 23.9 million had been received by early 2026 according to the PDNA, while the UN’s March report put the figure at $ 23.4 million.


Land assessments


Final decisions on safe returns and new settlements depend on NBRI validation, which has made land assessment a bottleneck. 

A UN situation report of 20 March noted that thousands of residents in Badulla and Nuwara Eliya continued to occupy high-risk zones and that the NBRI was severely under-resourced. The UN developed a capacity-support proposal for drone-based hazard mapping, on-site engineering inspections, and ready-to-use slope stabilisation designs.

NBRI Landslide Research and Risk Management Division Acting Director Laksiri Indrathilaka said the institute had completed its part of the process.

“Up to 22 November 2026 – covering the one-year period since the Ditwah disaster – we received a total of 8,031 formal requests for assessments across districts. Within those 8,031 requests, there were 5,974 structures, including houses, commercial properties, and public buildings,” he said.

“However, when our officers go to inspect a location as requested by a divisional secretary, local grama niladharis and residents point out additional neighbouring sites out of safety concerns. Because of this, while we received 8,031 formal requests, on the ground our teams have physically inspected 13,320 locations.

“Out of those 13,320 inspected locations, we identified 1,709 locations as High Risk, 3,685 as Medium Risk, and 2,803 as Low Risk. New assessment requests are still coming in daily, so the total count is being continuously updated.

“For the 1,709 high-risk locations, those families must be resettled in safe places, and the NBRI also has to inspect the resettlement lands. There are two types of resettlement sites: group settlements and individual settlements. We received requests for 840 group settlement sites and 10,220 individual settlement sites. Out of those, we have already inspected 839 group sites and 9,024 individual sites.”

Indrathilaka said that in terms of approved land capacity, the NBRI had recommended 2,831 acres of group settlement land as suitable for resettlement, while for individual settlements, it had approved 6,260 plots. He noted that allowing minimum space for roads and drainage at roughly 10 families per acre, the 2,831 acres in group sites could accommodate 28,310 families. “Combined with the over 6,000 individual plots, we have inspected and cleared land sufficient to resettle 34,000 families,” he added. 

“In reality, only about 1,700 high-risk families need to be relocated, yet the NBRI has already inspected, cleared, and issued official reports for land capable of housing 34,000 families – far more than double the required capacity. 

“People complain that the NBRI hasn’t conducted inspections, but we have inspected land for double the required families. If funding is available and implementation officers carry out their work, there is enough land cleared. The NBRI’s technical assessment mandate is complete and the remaining implementation responsibility lies with the other relevant institutions,” Indrathilaka said.

He added that complete district-wise and report-by-report data, including unsuitable land and exact acreages, were available, and that the work had been done by officials physically going into the field.


Families still waiting


CCMR Convenor Selvaraja Rajasegar said that although comprehensive statistics were unavailable, land had been identified for only a small proportion of the displaced Malaiyaha families. The worst-affected districts were Badulla, Matale, and Nuwara Eliya, followed by Kandy and Kegalle. He said Government assistance, including an initial Rs. 25,000 payment and proposed rental allowances, had reached only a limited number of families.

“We can’t say that relief was given to everyone. It was only given to a limited group. Similarly, land to build houses has only been selected for a small number so far. It has now been a year and not a single house has been built yet,” he charged.

Rajasegar noted that at development committee meetings in Badulla and Nuwara Eliya, the President had asked where land for plots of six or seven perches could be found, and that estate managers had replied that certain lands were suitable for tea cultivation. He also pointed out that State-owned Janatha Estates Development Board (Janawasama) estate lands had recently been approved for leasing while affected families on the same estates remained without permanent housing.

“Can’t houses be built even on land where there are thriving tea bushes? Some of those lands might be safe lands that are not prone to landslides,” he said.

He said around 10 families were living in a green-leaf weighing shed, locally known as a dalu maduwa, in Agarathenna, and others were in tents at an estate in Nuwara Eliya and in camps around Ury Estate in Badulla, while severely damaged houses at High Forest Estate No. 1 in Nuwara Eliya remained occupied despite visible cracks.

“In one of the houses I visited, a crowbar could be pushed deep into the cracks inside the house. The entire estate is almost condemned,” he said.

Some residents have returned to homes in areas the NBRI classes as high or moderate risk because they have nowhere else to go, and some have been advised to move temporarily to schools or kovils when rainfall reaches 100 mm. Rajasegar said that rental assistance was difficult to use because most estate accommodation consisted of line rooms.

“There are no standalone houses, so there is a question of where they can find a place to rent. Either the entire area has been declared high-risk, or there simply aren’t any houses to rent within the estate. There are only line rooms. If they need to rent, they have to look further, in a town or another village,” he said.

He said that plantation workers had continued working through the rains and landslides but had been given no date for support, there were no figures on children who may have dropped out of school, and some Nuwara Eliya vegetable farmers had received limited compensation that was insufficient. The CCMR has raised its concerns with the Plantation Minister and Deputy Minister, but nothing has been implemented.

Private Secretary to the Deputy Minister of Plantation Sivanesan described progress as “50-50”. Some families have left the estates to purchase land or houses elsewhere, while others are awaiting allocations within the estates.

“Many of the Malaiyaha people have already been given Rs. 5 million to buy land and purchase a house elsewhere, and many have already moved out,” he said.

He acknowledged that the process had seen delays, partly because the community had historically lacked legal ownership of the land on which it lived, which required a separate gazette notification and Cabinet paper. Land availability is another obstacle.

“Even if the estates or companies provide land, in many places the land fails to meet the requirements in the NBRI report,” he said.

Land had to pass an initial assessment and a second once plots were blocked out, he explained, and a failed plot meant starting again. Some families were also reluctant to move to sites further from their communities, he said, citing a plot seven kilometres away at Karawita Ella in Ratnapura, with road and school access, to which some residents had objected. Foundation stones have been laid for some projects, and Minister of Plantation and Community Infrastructure Samantha Viddyarathna has attended several ceremonies.

“A compensation programme has also been commenced for those who suffered partial damage. They have not been neglected, although there have been minor delays in this process. Nevertheless, the work is under way, which is why I said it’s 50-50. Some cases have been completed, while work on others is still in progress,” he said.

He said a small number of families lived in houses built without estate management permission, which required separate consideration. He noted that the ministry had no programme to allocate agricultural land, which would fall under the Ministry of Agriculture.


Donations awaiting expenditure


Speaking to The Sunday Morning, Senior Additional Secretary to the President and Rebuilding Sri Lanka Presidential Task Force Secretary G.M.R.D. Aponsu said about Rs. 11 billion in local and foreign contributions, from identified and anonymous donors, remained undistributed. 

He said that projects, including the reconstruction of damaged hospitals and schools, had been identified, and that line ministries had submitted proposals to the National Planning Department.

“We will coordinate the donor contributions with the projects. We are going to discuss with the known donors as well. We will inform them about the specific project funded through their contributions and monitor their progress,” he said.

Aponsu clarified that the fund was not designed to compensate affected households directly, as assistance for damaged houses was being provided separately through Government funds.

“The Government has sufficient funds of its own and has been using those. Therefore, nothing has been spent from the donations yet,” Aponsu said.

He said that disbursements were expected to begin next year, following the recently received Cabinet decision.

The fund has also drawn scrutiny. National Audit Office officials, including Auditor General Samudika Jayarathna, told Parliament’s Committee on Public Finance (COPF) in June that no statutory fund named ‘Rebuilding Sri Lanka’ had been legally established, and that donations were held in a special account under the Deputy Secretary to the Treasury. 

COPF Chairman Harsha de Silva and members questioned how such an account was audited, how donor sources were verified, and how spending was monitored. Civil society groups raised concerns about the Management Committee’s all-male composition at its establishment, its heavy business representation, and its unclear mandate on vulnerable groups, gender, and the environment.

In April, Deputy Minister of Finance and Planning Dr. Anil Jayantha Fernando said that Rs. 9,583 million had been collected from 49 countries as of 24 April and was securely held in the Treasury with no irregularities. Government officials noted that around Rs. 200 billion in Treasury allocations had already been used for relief and recovery.


Communication gaps


Grid failures, fuel shortages, and severed fibre backbones took thousands of mobile towers offline due to Cyclone Ditwah, while submerged low-lying equipment sites slowed repairs. 

In the Uva Province, where at least six major bridges were destroyed, Provincial Director of Health Services Dr. Mahendra Senevirathna said that telephone and cellular communications had broken down completely. Health leaders and hospitals were isolated, unable to coordinate evacuations or check on their own families. 

Nationwide, 243 health facilities were damaged, and 90,127 people in Uva, roughly 25% of those affected, were directly affected.

Dr. Senevirathna stated that equipping remote health facilities and regional administrative offices with Starlink satellite internet was a recommendation in the health authorities’ disaster management plans, proposed as an essential baseline, at minimum for regional administrative offices. He said it would keep medical reporting, patient transfer requests, and command communications running when towers and landlines failed. 

Uva authorities have also added communication drills and contingency reporting hierarchies to provincial plans, and are documenting their response experience in consolidated reports.

The UN’s 6 March report also flagged inconsistent communication about eligibility criteria and procedures, together with limited grievance mechanisms and legal advice, which it said had undermined trust and equitable access to support.


Protecting the central highlands


A committee report recommending a Central Highlands Environmental Authority (CHEA) was submitted to the Cabinet in August, and a President’s Media Division official told The Sunday Morning that the Government expected to enact the legislation in 2027. 

The authority would function along similar lines to the Mahaweli Authority, with its establishment supported by an ADB-funded project, and would cover ecologically sensitive areas above 5,000 feet, with powers over forest conservation and land use, including halting unauthorised development.

Speaking at a housing handover in Bandarawela on 28 August, President Anura Kumara Dissanayake said that the central highlands were witnessing mountain collapses, the drying up of springs, and the silting of rivers.

“Under this programme, some people may lose their homes. Areas currently used as agricultural land may have to be converted into forests. But this has to be done. Otherwise, we will face a major disaster. The powers of institutions will be redistributed, positions may shift from one institution to another, and job titles may change. No one needs to panic,” the President said.

The President first signalled the plan during the 2026 Budget debate, proposing a blanket ban on construction above 5,000 feet. Environmentalists and experts have questioned the threshold, arguing that a restriction based solely on elevation lacks a scientific basis and urging reliance on the National Physical Planning Policy and Plan 2050. They noted that much of Nuwara Eliya, including the city, lay at or above that elevation, and warned of consequences for the tea industry, tourism, and livelihoods.

Meanwhile, the National Planning Department is formulating a national disaster recovery framework, which, according to the PDNA, will set beneficiary selection criteria, define inter-agency roles, align recovery spending with annual budgets, and manage concessional financing from development partners.


Box 1

Compensation rollout

While the Government earmarked Rs. 500 billion for overall post-Ditwah reconstruction, a World Bank assessment released in October 2026 revealed that only about 8% (approximately Rs. 40 billion) of the total allocation had been disbursed by mid-year.

Internal Government figures mirror this bottleneck. According to data from the Disaster Management Division, out of Rs. 86.7 billion released specifically between January and July this year for compensation payments and infrastructure rebuilding in flood- and landslide-hit districts, only Rs. 26.4 billion (30%) had been utilised by 31 July. 

That left Rs. 60.3 billion sitting unspent, prompting the division’s Additional Secretary to issue a directive on 12 August instructing district secretaries to accelerate disbursements without further delay.

The disbursement gap is sharpest between immediate relief and permanent relocation. By 31 July, authorities had distributed 85% of the Rs. 7.6 billion released for urgent immediate assistance. Under Treasury Budget Circular No.08/2025, short-term, unassessed cash grants moved quickly through divisional secretariats. 

Official data from the Ministry of Public Administration, Provincial Councils, and Local Government shows the flagship Rs. 25,000 one-time house-cleaning allowance – granted per housing unit regardless of ownership – reached 423,914 out of 434,375 eligible households (97.6%). 

Similarly, the Rs. 50,000 one-time grant for replacing damaged kitchen utensils and essential household items was disbursed to 115,757 of the 163,509 eligible housing units (70.8%) during the initial rollout, alongside Rs. 15,000 one-time school supply allowances paid to over 141,382 affected students.

In contrast, permanent resettlement programmes have lagged behind. Out of Rs. 1.05 billion set aside specifically to relocate displaced families, only Rs. 190 million (18%) had been spent by the end of July, leaving Rs. 868 million unutilised. Earlier in the year, humanitarian coordination reports from the United Nations Office of the Resident Coordinator in Sri Lanka also flagged that thousands of displaced families remained in rented accommodation without a clear exit strategy.

Government disclosures to Parliament show the scale of the housing backlog. Of the 29,983 families requiring resettlement, only 1,615 had been permanently relocated, with safety clearances and verification hurdles cited as the primary causes of delay. More than 50,000 households were still awaiting second-instalment housing payments, while 7,536 complex cases involving fully damaged homes had been referred to special review committees.

Delays have been particularly acute in land and property acquisition schemes. Payments to households that chose to buy an existing house had reached only 678 of 5,175 identified families, leaving 4,497 pending. Among those who opted to buy land and build, 208 of 1,964 families had received funds, leaving 1,756 pending. 

Officials and Opposition MPs attributed these bottlenecks to ownership verification disputes, application discrepancies, rejected claims, and unauthorised constructions that fell outside standard payout rules.

For approved fully damaged homes, the Rs. 5 million construction entitlement is released in three tranches tied to building milestones – an initial Rs. 2 million followed by two instalments of Rs. 1.5 million. Under bilateral reconstruction reviews in late November, India confirmed its readiness to fund the Rs. 2 million first instalment for 5,400 completely destroyed homes and Rs. 500,000 each for partially damaged houses, as part of its $ 450 million post-Ditwah package.

Targeted regional and sectoral disbursements have shown incremental progress in recent weeks:

  • Colombo and estate sector: In the Kolonnawa electoral division in Colombo, initial payments for partially damaged homes had reached 17,756 homeowners out of a Rs. 10 billion allocation – including 1,004 new cheques distributed on 20 November – while 1,300 beneficiaries had received second instalments, according to the Government’s News.lk. Elsewhere, compensation disbursements had begun for 1,268 identified estate houses.
  • Resettlement and transitional shelters: Completed houses under the Rs. 5 million national construction programme were handed over in Anuradhapura, at Nachchaduwa and Eppawala, on 25 November. In the central highlands, 135 transitional shelters were built with support from the International Organization for Migration (IOM) Sri Lanka and Japan, while 30 acres of land were released in Ududumbara for 114 displaced families.
  • Agriculture: The Department of Agrarian Development announced that compensation had been fully provided to all affected farmers, with Rs. 8.886 billion disbursed to 112,442 farmers covering 59,245 hectares. Meanwhile, 95% of farmers – 667,460 cultivators across 449,750 hectares – had received the Yala season fertiliser subsidy at a total expenditure of Rs. 13.492 billion.
  • Small businesses: Following Budget Circular No.08/2025(iii) issued on 22 January this year, registered micro, small, and self-employed businesses were made eligible for one-time reopening grants of Rs. 200,000, and Rs. 50,000 for unregistered home-based enterprises. Under a parallel Rs. 10 billion concessional loan scheme implemented across 15 banks at a 3% annual interest rate, the Prime Minister’s Office reported that Rs. 3,812 million had been disbursed to 2,800 entrepreneurs as of 28 April.


Box 2

Transport infrastructure

Cyclone Ditwah caused an estimated $ 973 million in transport sector damages across Sri Lanka, according to the World Bank. 

The Government has shifted from emergency clearance to permanent, climate-resilient reconstruction. On 19 November, authorities inaugurated a dedicated Disaster Reconstruction and Rural Road Project Management Office in Koswatta, Battaramulla, operating under the Ministry of Transport, Highways, and Urban Development via four regional Project Implementation Units (PIUs).

Backed by a Rs. 168 billion financial allocation, the integrated recovery programme targets the completion of 285 Ditwah-damaged rehabilitation projects alongside 756 rural road development projects throughout 2027. 

Major international financing includes $ 110 million from the World Bank, approved in September to rebuild 600 km of climate-resilient roads across eight districts, alongside loan packages from the Asian Development Bank (ADB) and the Japan International Cooperation Agency (JICA).

Out of 820 damaged locations recorded on A- and B-class highways, 330 restoration projects have reached 75% completion, while work on the remaining 490 sites has been structured into 120 contract packages. In November, the Cabinet approved Rs. 9.1 billion in road contracts, including a dedicated Rs. 763.98 million contract awarded to ELS Construction Ltd. to rehabilitate cyclone-damaged road sections in the Nawalapitiya area. 

Rural rebuilding has also restored critical estate arteries, such as the main access road in Park Estate, which reopened in November after isolating over 1,500 residents and disrupting tea transport for nine months.

Bridge reconstruction has simultaneously gathered pace through bilateral assistance. Reconstruction began on 1 November for nine of the 14 bridges completely destroyed by the cyclone under a Chinese-assisted programme undertaken by the China State Construction Engineering Corporation (CSCEC) across five provinces. Backed by Rs. 3.95 billion in Chinese assistance, the permanent bridges carry an 18-month completion timeline. 

Meanwhile, following the installation of 11 temporary Bailey bridges across 10 locations for immediate post-cyclone access, India launched permanent bridge construction in September starting with the Moragahakanda Bridge in Matale, with work scheduled across 12 additional permanent bridge sites.

Restoration work is also ongoing across the railway network, particularly along heavily damaged sections of the upcountry railway line and corridors such as the Batticaloa–Polonnaruwa line. 

Under an INR-denominated $ 250 million Indian Line of Credit, permanent railway infrastructure works include constructing a new railway bridge in Peradeniya and rehabilitating damaged tracks and signalling systems, while dedicated freight corridors – including the limestone railway line from Aruwakkalu to Puttalam – were restored earlier in 2026 to resume industrial logistics.