- No compensation entitlement as LOI remains unissued: Energy Min. officials
- Project’s official termination yet to be announced?
Yet another controversial mega-investment, backed by successive policy decisions, appears to be heading towards an end in Sri Lanka, with the proposed $ 3.7 billion Sinopec oil refinery in Hambantota, once promoted as the country’s largest-ever Foreign Direct Investment (FDI), now facing the prospect of termination.
The project has reached a stalemate after nearly four years of negotiations, with disagreements over domestic fuel market access, tax concessions, land allocation, and other investment conditions undermining its progress.
The proposal had also triggered considerable debate among the country’s energy experts and within sections of the National People’s Power (NPP) Government, with concerns raised over the potential setbacks to Sri Lanka’s domestic energy industry, energy security, and long-term energy policy if the refinery proceeded under the proposed terms.
The entire debate finally ended when the Cabinet-Appointed Negotiating Committee (CANC) recommended terminating the proposed agreement with China’s State-owned energy giant Sinopec, calling for fresh investment proposals but not officially announcing it has been terminated.
However, the recommendation did not amount to an official cancellation, an expert said. The final decision rests with the Cabinet of Ministers, which has yet to formally decide whether to terminate the project or reopen the procurement process.
The major stumbling block appears to have been Sinopec’s demand to increase the proportion of refined petroleum products allocated to Sri Lanka’s domestic market from the originally proposed 20% to 40%, while retaining the remaining 60% for export. The Government informed the investor this, but there was no settlement on the agreement.
Under the original investment framework, the refinery was conceived primarily as an export-oriented facility, with 80% of its production earmarked for overseas markets and only 20% for domestic consumption.
The disagreement over this arrangement became one of the most contentious issues in negotiations, with Government officials concerned that allowing a higher proportion of refinery output into the domestic market could undermine the operations of the existing Sapugaskanda Oil Refinery and create intense competition in the local petroleum industry.
An industry source familiar with the negotiations told The Sunday Morning that the Government had maintained that it could accommodate only 20% of the proposed refinery’s production for the domestic market.
“The investor wanted to increase the domestic allocation from 20% to 40%. We maintained that we could accommodate only 20%. This was a major disagreement and one of the reasons the project remained stagnant,” the source said.
The Government had also raised concerns about the potential impact on Sapugaskanda, including local refining, employment, and the wider domestic petroleum industry, should both refineries compete for a larger share of the local market, an official at the Ministry of Energy said.
The source said the Government had communicated its position that the domestic market could not absorb the additional allocation without potentially affecting existing operations. However, the investor was reportedly unwilling to proceed under those conditions. Apart from market access, disagreements over taxation, land, and water requirements also contributed to the deterioration of negotiations.
Energy expert questions Sinopec deal’s commercial rationale
Commenting on the CANC’s reported recommendation to terminate the Sinopec project, an energy expert questioned the commercial rationale behind the concessions sought by the Chinese investor, arguing that Sri Lanka should not offer tax holidays or legally guaranteed domestic purchases to attract a refinery investment.
He stressed that he was not an insider to the negotiations and that his assessment was based on publicly available information and concerns he had raised publicly in December 2025.
According to him, the conditions reportedly sought by Sinopec went beyond the original terms of the Expression of Interest (EOI) and Request for Proposal (RFP) to which the company had responded. He recalled that the proposed tax holiday was approximately 25 years, although he cautioned that the precise period needed to be verified against the original procurement documents and subsequent negotiations.
The expert also questioned the reported request for a commitment that domestic buyers purchase 40% of the refinery’s output, compared with the 20% allocation he understood to have been specified in the original EOI. He expressed opposition even to the original 20% domestic offtake arrangement, arguing that the Government should not legally guarantee purchases from a particular refinery.
Furthermore, he questioned which entities would ultimately be required to purchase the fuel, including the Ceylon Petroleum Corporation (CPC), Shell, Sinopec, Lanka IOC, or other distributors, noting that the contractual obligations and fine print would be critical in assessing the implications for the domestic petroleum market. A legally guaranteed domestic market, he argued, could make Sri Lanka dependent on the proposed Hambantota refinery and the existing Sapugaskanda facility for a substantial proportion of its fuel requirements.
He maintained that an investor claiming a competitive advantage from Hambantota’s geographical location should be able to compete commercially without requiring tax concessions or guaranteed local purchases.
“If the refinery can produce fuel at a competitive price, local distributors should be able to purchase from the lowest-priced supplier. There is no reason to guarantee a market for one particular investor,” he argued. He said that the Government should assess the project on its commercial merits rather than make concessions that could constrain future energy policy decisions.
The energy expert also questioned whether the investor’s negotiating position indicated a genuine commitment to proceed or an attempt to establish grounds to withdraw from the project. He suggested that China’s investment appetite in higher-risk countries may also have influenced the negotiations.
He also referred to a report by the Auditor General’s Department, urging that the report and relevant Cabinet decisions be examined to establish the official position and the reasoning behind the recommendation of the project in the first place.
Drawing a comparison with Singapore, he said that Sri Lanka could potentially develop Hambantota into an energy and maritime services centre despite not being an oil-producing country. Hambantota, by contrast, already has a developed port, making it a potentially practical alternative. However, he maintained that the location alone did not justify granting an investor tax concessions or guaranteed domestic sales.
On 12 August 2025, Sinopec reportedly sought substantial revisions to the original investment conditions, prompting the Energy Ministry to prepare a fresh Cabinet memorandum outlining the proposed terms and conditions. Among the major requests were a 25-year tax holiday, greater access to Sri Lanka’s domestic petroleum market, and amendments to the original tender conditions.
While the committee had recommended terminating the proposed arrangement and inviting fresh proposals through a new RFP, the Government has not yet announced a final Cabinet decision.
No compensation
Energy Ministry sources also indicated that no compensation provision had been triggered, as the procurement process had not reached the stage of issuing a Letter of Intent (LOI) to the investor. The project therefore remains at the tender and negotiation stage rather than an executed investment agreement that has proceeded to implementation.
The timeline
From H’tota’s industrial ambitions to Sinopec proposal
The Hambantota refinery proposal did not originate under the incumbent NPP Government. The development of Hambantota as a major industrial and logistics centre was pursued during former President Mahinda Rajapaksa’s administration, which initiated several large-scale infrastructure and industrial development projects in the Southern Province.
A separate refinery proposal subsequently emerged under the Ranil Wickremesinghe Government in 2019, involving Hambantota Oil Refinery Ltd., with a proposed investment linked to Singapore and Oman’s Ministry of Oil and Gas.
The Sinopec proposal, however, developed through a separate procurement process initiated under the Government of President Wickremesinghe and Energy Minister Kanchana Wijesekera.
Its origins can be traced to December 2022, when Sinopec also entered into a separate commercial arrangement involving Sri Lankan products. On 2 December 2022, the Foreign Ministry announced that Sinopec had entered into an agreement with Beijing Sri Road Connection Trade Company Ltd. to import and market Sri Lankan products through its extensive network of convenience stores in China.
The agreement, valued at more than $ 800,000, was signed by Beijing Sri Road Connection Trade Company Chief Executive Officer Chiranjaya Udumullage and Sinopec Deputy Manager – International Sales Wang Qian. The agreement followed Sri Lanka’s participation in the fifth China International Import Expo (CIIE), held in Shanghai from 5 to 10 November 2022.
Evolution of refinery proposal – 2022–’23
The formal process for the proposed Hambantota refinery began on 23 December 2022, when Energy Minister Wijesekera submitted the initial Cabinet Memorandum No.221217/1621/036. The memorandum proposed an export-oriented petroleum refinery and an associated product-processing centre in Hambantota.
On 9 January 2023, the Cabinet approved the proposal to invite investors and select a suitable investor for the project.
In February 2023, the Ministry of Power and Energy, together with the Board of Investment (BOI), invited EOIs from investors for a Build-Own-Operate (BOO) refinery.
On 13 March 2023, a Sinopec delegation met then President Wickremesinghe and presented its proposal to develop an oil distribution hub and refinery in Hambantota. The Chinese company offered to fully finance the proposed investment. The initial project value was estimated at approximately $ 4.5 billion before being revised to $ 3.7 billion.
Between March and July 2023, seven companies expressed interest in the project. Sinopec and Vitol were subsequently shortlisted. On 9 November 2023, Minister Wijesekera submitted Cabinet Memorandum No.40/2023 recommending Sinopec as the preferred investor for the proposed refinery. The Cabinet subsequently approved Sinopec’s selection to establish the export-oriented petroleum refinery.
The project was strategically significant because of its proposed location adjacent to the Hambantota International Port, which is operated by China Merchants Port Holdings under a 99-year lease. The refinery was expected to facilitate the processing and export of petroleum products through the port, strengthening Hambantota’s position as a regional energy and logistics hub.
NPP Govt. inherits project
When President Anura Kumara Dissanayake’s NPP Government assumed office in September 2024, the Sinopec refinery proposal was already at an advanced stage of the investor selection process.
A major milestone came on 22 January 2025, during President Dissanayake’s State visit to China, when Sri Lanka and Sinopec signed an agreement in Beijing to fast-track the proposed $ 3.7 billion refinery. Foreign Minister Vijitha Herath signed on behalf of Sri Lanka.
The proposed refinery was designed to have a capacity of 200,000 barrels per day and was presented as the largest single FDI in Sri Lanka’s history. The Government viewed the project as an opportunity to attract substantial foreign capital, strengthen the country’s energy infrastructure, increase export earnings, and create employment.
Nevertheless, the signing of the January 2025 agreement did not mean that all commercial, regulatory, and procurement conditions had been finalised. The subsequent negotiations over taxation, domestic market access, and other investment requirements demonstrated that considerable differences remained between the two parties.
Aug. 2025: Govt. seeks revised investment conditions
The disagreements became increasingly apparent in August 2025, when Sinopec reportedly sought revisions to the original conditions.
On 12 August 2025, the Energy Ministry prepared a fresh Cabinet memorandum addressing the terms and conditions of the investment, including the reported request for a 25-year tax holiday and increased access to the domestic fuel market.
The proposed revisions raised questions about whether the Government could accommodate the investor’s demands without undermining its revenue commitments and the existing petroleum industry.
The ministry also faced questions about the contents of the Memorandum of Understanding (MOU), the allocation of land, the proposed additional land requirements, and the conditions under which the investment would be implemented.
On 31 July 2025, a Right to Information (RTI) application was submitted by this writer to the Ministry of Energy under reference number ADM/7/5/4, seeking details of the project. The application sought the latest updates on the investment, a copy or summary of the key terms, the contents of the MOU, and the conditions imposed by Sinopec and the Sri Lankan Government.
However, the ministry declined to disclose the requested information, citing provisions of the RTI Act No.12 of 2016. The Additional Secretary for Human Resources maintained that information concerning the MOU and the other requested investment conditions could not be provided until the procurement process was finalised.
Environmental assessment and project preparations
Despite the uncertainty surrounding the commercial negotiations, preparatory work associated with the proposed refinery had also progressed.
Kenneth EHS Consultants, partnering with Skills International Ltd., announced its involvement in providing specialised petroleum health, safety, environment, and fire safety inputs for the Environmental Impact Assessment (EIA) assignment.
The consultancy described the proposed refinery as one of Sri Lanka’s most significant infrastructure developments, highlighting its planned capacity of 200,000 barrels per day and its strategic location alongside Hambantota International Port. The project remained dependent on the finalisation of procurement and commercial conditions. The uncertainty continued into 2026 and the broader commercial disagreements remained unresolved.
By July this year, there was still no final Government decision on proceeding with the project. On 6 November, the Energy Minister indicated that a decision on the refinery would take another two months. Finally, it came to the point of no return.